Point Lepreau restart may be ahead of schedule
Point Lepreau restart may be ahead of schedule: http://www.cbc.ca/news/canada/new-brunswick/story/2012/07/20/nb-point-lepreau-restart-627.html
...great to see some positive news: 'The Point Lepreau Nuclear
Generating Station’s refurbishment project is in the homestretch and is
starting to hit some of its deadlines earlier than expected.
The refurbishment project is three years behind schedule and more than $1 billion over budget.
NB Power is now getting some positive reports about the refurbishment
project’s restart timeline. However, the Crown corporation and the
provincial government are refusing to talk about it publicly.
Point
Lepreau is not scheduled to be running at full power until the end of
September, but there have been signs for months that it could happen
earlier."